LEADERSHIP
CONSTRUCTION CONTINUES
ON CORPORATE ADDITION
This series of photos shows the progression of the third wing
addition at the corporate office from April 2020 to July 2021.
The addition will provide about 38,000 square feet of new
space. It is anticipated to open for use in 2022.
Clockwise, starting above: The rear of the corporate office is shown
in April 2020 shortly after Davey crews cleared trees and brush so
construction could start on the third wing addition.
Construction crews are seen in January starting construction on the
corporate third wing addition site.
Excavators move earth in March to make space for the basement of
the third wing.
The concrete walls of the basement take shape in April.
Steel beams arrived this summer and give shape to the structure
of the addition.